Electrical and Instrumentation services
Project Type: الاعمال الكهربائية والاجهزة الدقيقة
The WORK includes the following activities:
Part 1:
- Cable trench
- Auger boring
- Installation of HV joint pit
- Installation of cable maker and earthing pit
Part 2 :
(Power,
instrumentation, earthing, FOC) according to the cable schedule listed below:
The cable laying work include:
- Load, haul and offload the cable drums from Company warehouse to the location on site as required.
- Cutting and measure
insulation resistance of the cable reels as delivered to site.
- Stamping and fixing of
cable identification tags, temporary sealing of cable ends.
- Cable protection and temporary capping for the ends of cables including ends of cable on drums or coils after cutting.
- Cleaning conduit pipes, ducts, duct banks, and trays, cabling through sleeves, sealing of duct bank and the like.
- Determining required cable length at the tail end for connection to the equipment.
- The residual length on each drum after cutting shall be clearly marked on the side of the drum.
- Rollers shall be used for cable pulling, the rollers shall be well maintained and in good working order.
- When cables are installed but cannot be immediately terminated, they shall be coiled up at the terminal point in a neat an orderly manner.
- Provide and install PVC conduit for cable laying as per drawings.